Kangra Coal invests in a life of mine beyond 2031

Kangra Coal invests in a life of mine beyond 2031

Coal mining company Kangra, a subsidiary of mining investment company Menar, is nearing the completion of the construction of the Twyfelhoek Adit, which forms part of the Kusipongo coal reserve in South Africa.

Construction on the project, in Saul Mkhizeville, Mpumalanga, started on 6 April 2021 and is on course to be completed by mid-December 2021, with the first coal expected by the first quarter of 2022.

According to Kangra General Manager Pierre Louw, Twyfelhoek has met all the regulatory requirements. “The company has allocated a capital budget of R153.6-million to establish the shaft and the project is progressing well. The access road to the Adit was completed on 13 September 2021 and the powerlines and the water reticulation connection will be completed by mid-December 2021,” says Louw.

Completing the project meant that several families living within 500m of the mine had to be relocated. Kangra is in the process of building the families new homes using local contractors. The construction of the new homes will be completed by the first quarter of 2022.

Investing in new mining equipment

Kangra also invested in new and reconditioned mining equipment to the value of R45-million to mine the Kusipongo reserves. As part of the mine’s Social and Labour Plan commitments, a project will commence in the first quarter of 2022 to supply water to the Donkerhoek community. Kangra will invest approximately R20-million into the Social and Labour Plan commitments for the next five years.

“The Kusipongo reserve is located to the west of the existing mining operation and is a natural extension of Kangra’s current coal resource. It has a coal reserve of around 41.9 million tons and could potentially extend the life of the mine by more than 20 years,” says Louw.

He adds that the underground reserves will be accessed through three adits namely: Twyfelhoek, Balgarthan A and B. There is a capital budget of approximately R58.2-million for Balgarthan A and construction will start as soon as all authorisations are approved.

With a mixture of both low and high volatility coal, the Kusipongo reserve will be mined from three sections using a board and pillar method. Kangra is targeting a production rate of 1.44 million tons per annum from the underground mining sections and 360 000 tons per year from the available opencast areas for the duration of the life of mine.

Once mined from the various shafts, the coal will be trucked/conveyed to the Maquasa East shaft. From here, it will be washed and trucked to the Panbult Rail Siding, which is about 30km from the mine where it will be railed to the Richards Bay Coal Terminal (RBCT), in KwaZulu-Natal.

Kangra started mining the Block C opencast section in February 2021. The Block C opencast pit production will be ramped up to 40 000 tons a month of run-of-mine coal once the establishment of the Twyfelhoek shaft is completed.

“The last couple of years have been challenging for our staff members and the community, particularly when the mine was placed under care and maintenance owing to the onset of the Covid-19 pandemic and the ensuing collapse of the coal price. Many of our employees have been uncertain about their jobs,” says Louw.

WhyAfrica provides you with business intelligence that matters. WhyAfrica specialises in African affairs and natural resources. Africa is our business, and we want it to be yours too. To subscribe to WhyAfrica’s free newsletter or digital magazine, and for more news on Africa, visit the website at www.whyafrica.co.za or send a direct message. WhyAfrica will launch its first ever digital magazine in November. If you are interested in contributing or advertising, please contact me at leon@whyafrica.co.za. To coincide with the first launch, we have a range of different packages and combo deals to give your company the greatest exposure to a rapidly growing, African readership.       

 